Apr 11 2008
GATC Remodeling - New Updates!
SPIN ROOM FLOOR
We finished our first construction project of the year…the installation of a new Ramflex Mondo floor in the spin room. I want to thank each of you for your patience and cooperation as we had to move bikes, move classes, etc. I hope each of you have had a chance to spin on the new floor. It looks great and is much better for your health.
LOCKERS
We are anticipating an install date of anywhere from late May through June for the men’s and women’s athletic club lockers. We will have a display board set up in the lobby about two weeks prior to the install so you can see the lockers, learn how to use the new locks, etc. For those of you who hold Executive full or half lockers, you will be receiving a letter from Lisa Thomas with information on when we need you to vacate your locker so we can change out your old locker for a new locker. The good news is that all work will be done in the evening hours after we are closed.
CONTRACTOR MOBILIZATION
i2 Construction is the contractor for the weight room and business office expansion. They will be mobilizing the week of April 28 with the installation of construction fencing, equipment, etc. They will be located in the first row of parking on the east side of the building adjacent to the handicap parking stalls. This allows them the closest access to the construction site. This area of the parking lot will not be available for parking through the end of September, beginning of October. We realize the impact this will place on close proximity parking. We appreciate your patience and cooperation as we “Make the Best Part of Your Day…Even Better”.
GRADING AND EXCAVATING
We will be breaking ground the week of May 5 with grading and excavating. You can expect to see construction equipment in the mobilization area and the grass area to the south and east of the building (adjacent to outdoor
tennis court #1).
TENNIS PLAYERS
We will do our best to keep all five outdoor tennis courts in full operation during the construction. Please know that courts 1 and 2 are adjacent to the construction site and will incurr dust and noise at various times during the construction. After April 28, access to court 1 will be through court 2.
Paula Neubert, General Manager